Western Gateway Weekly Update 7 - September 22, 2022

Mary Ricker said over 2 years ago:

Construction is officially underway for the City of Shelton's Western Gateway project. Please share this information with your neighbors and encourage them to sign up to receive email updates.

Upcoming Work and Construction

Next week, crews will continue working on installing the 12" water main from 12th Street eastward. Pipe services installation work will continue for a couple of days later next week.

What to Expect During Construction

The project contractor is continuing to work a "4 10s" (10-hour workdays, 4 days a week) project schedule until further notice.

Continue to expect heavy congestion while crews and equipment are working. Working hours will typically be 10-hour windows between 7 a.m. and 5 p.m. on weekdays. Please be patient with crews as they work to keep delays to a minimum during this project.

Driving lanes will be narrow and heavy equipment/trucks will be entering and leaving work zones. Please be alert and obey flagging personnel for your safety and others! Plan accordingly and use alternate routes when possible. 

Project Updates

This is a major project for us, and we'll be sharing project updates in a variety of places. You can follow the City's Facebook or Twitter accounts. We have also created a project webpage on our City website - sheltonwa.gov/westerngateway. A link to this webpage has been added to the homepage of the City's app.

We'll also share weekly updates here, and you can sign up to receive an email notification when a new update is available.