Click this link to optimize Open Town Hall for screen readers Skip to Content
Open Town Hall
Opengov

Follow along here for Western Gateway updates.

← Previous   Next →

Western Gateway Weekly Update 6 - September 15, 2022

Mary Ricker said over 2 years ago:

Construction is officially underway for the City of Shelton's Western Gateway project. Please share this information with your neighbors and encourage them to sign up to receive email updates.

Upcoming Work and Construction

Crews are continuing to install pipe services throughout the project area. Drivers should plan for 15-20 minute delays to travel through the work zone.

What to Expect During Construction

The project contractor is working a "4 10s" (10-hour work days, 4 days a week) work schedule until further notice. 

Continue to expect heavy congestion while crews and equipment are working. Working hours will typically be 10-hour windows between 7 a.m. and 5 p.m. on weekdays. Please be patient with crews as they work to keep delays to a minimum during this project.

Driving lanes will be narrow and heavy equipment/trucks will be entering and leaving work zones. Please be alert and obey flagging personnel for your safety and others! Plan accordingly and use alternate routes when possible.

Project Updates

This is a major project for us, and we'll be sharing project updates in a variety of places. You can follow the City's Facebook or Twitter accounts. We have also created a project webpage on our City website - sheltonwa.gov/westerngateway. A link to this project webpage has been added to the homepage of the City's app.

We'll also share weekly updates here, and you can sign up to receive an email notification when a new update is available.

0 comments

This post is now closed to comments

To write a comment, your browser needs to accept cookies from communityfeedback.opengov.com.

Read more >